Exam PgMP Topic 5 Question 230 Discussion
Actual exam question for PMI's PgMP exam
Question #: 230
Topic #: 5
Question #: 230
Topic #: 5
You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000.
The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule.
Based on this information, what is the schedule variance (SV) of this program?
The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule.
Based on this information, what is the schedule variance (SV) of this program?
Suggested Answer: D Vote an answer
Section: Volume A
by Xanthe at Mar 10, 2024, 06:21 PM
Contact Us
If you have any question please leave me your email address, we will reply and send email to you in 12 hours.
Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday
Support: Contact now
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).