Exam C_TS412_2021 Topic 3 Question 42 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 42
Topic #: 3
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question

Suggested Answer: A,D Vote an answer

To enable automatic assignment of material components to the project, you have to maintain the material master and the BOM item. The material master contains the data required for planning and procurement of materials. The BOM item contains the data required for assigning materials to a network activity or a WBS element. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

by Blair at Nov 29, 2023, 09:14 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어