Construction of a gymnasium is scheduled to be complete 365 days from the date of the notice to proceed. On Friday, day 355 of the schedule, the contractor submits a punch list to the architect for substantial completion.
The architect agrees to review the punch list on-site after the weekend.
On Monday, the architect discovers that a subcontractor left open a skylight over the weekend, allowing heavy rain to fall into the courtyard area and damage the gymnasium floor. It was determined the flooring must be replaced. The lead time for new flooring is 8-10 weeks, and installation will take 14 days. The architect's agreement with the owner is contracted to end 30 days after substantial completion.
Which of the following documents must the architect prepare immediately? Check the two that apply.
The architect agrees to review the punch list on-site after the weekend.
On Monday, the architect discovers that a subcontractor left open a skylight over the weekend, allowing heavy rain to fall into the courtyard area and damage the gymnasium floor. It was determined the flooring must be replaced. The lead time for new flooring is 8-10 weeks, and installation will take 14 days. The architect's agreement with the owner is contracted to end 30 days after substantial completion.
Which of the following documents must the architect prepare immediately? Check the two that apply.
Correct Answer: A,F
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A construction project is one week away from the date of substantial completion as defined by an AIA A201 agreement. The owner comes forward with a major change to the work. The contractor and owner disagree on how much to extend the contract time. The project needs to proceed without delay while the contractor and owner work out the difference.
Which one of the following steps should the architect take?
Which one of the following steps should the architect take?
Correct Answer: C
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
A project achieves refinement and coordination in which of the following phases?
Correct Answer: B
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
What is the primary purpose of a punch list?
Correct Answer: D
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).

Prior to the project kick-off, the architect requests to add an additional week of review time to the schedule for each design submission for coordination with their consultants. Based on the schedule provided, what is the earliest start date for construction with the additional review periods?
Correct Answer: C
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Which document authorizes the contractor to proceed with work?
Correct Answer: D
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Which of the following is a key advantage of using Building Information Modeling (BIM)?
Correct Answer: B
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).
Which insurance policy protects the architect against claims of negligence?
Correct Answer: A
Vote an answer
Explanation: Only visible for Fast2test members. You can sign-up / login (it's free).