Nokia SDM Certification - NI - SDM_2002001050 Exam Practice Test
What is the main advantage of site based operations (ordering-acceptance-invoicingpayment) towards the subcontractors.
Correct Answer: B
Vote an answer
Who is responsible to prepare the initial Project Plan for Gate 4 approval?
Correct Answer: D
Vote an answer
How would you handle performance problems related to RAN frequency planning in a project where customer is responsible for Network Planning?
Correct Answer: D
Vote an answer
What is the recommended action when customer asks for a consistency check to his network planning files which was not included in NSN scope of work?
Correct Answer: C
Vote an answer
What is the formula of the "value of risk" in the quantitative risk analysis?
Correct Answer: C
Vote an answer
A project got an engineer assigned with a competence level of 3, but should have one with at least a level 4. How does the PM react?
Correct Answer: A
Vote an answer
What is the first step that a PM needs to do when a project KPI is showing a huge variation compared to previous periods?
Correct Answer: A
Vote an answer
Which of the following statements about the project communication process is true ?
Correct Answer: D
Vote an answer
What needs to be updated after approved scope change request?
Correct Answer: C
Vote an answer
Why are PARD (Project Asset Rotation Days) and TILT (Telecom Implementation Lead-Time) KPI's closely related to each other?
Correct Answer: C
Vote an answer