AACE International AACE-PSP Certification Exam is a rigorous and highly respected certification program that demonstrates a candidate's knowledge and expertise in project planning and scheduling. Planning & Scheduling Professional (PSP) Exam certification is recognized globally and is highly valued by employers in the construction, engineering, and related industries. Passing the exam requires a strong understanding of project management principles and techniques, as well as a commitment to ongoing professional development.


To be eligible for the AACE-PSP certification, candidates must have a minimum of four years of professional experience in planning and scheduling. They must also have a bachelor's degree from an accredited institution, or a combination of education and experience that equals four years. Planning & Scheduling Professional (PSP) Exam certification exam consists of 120 multiple-choice questions, which cover topics such as project planning, scheduling, resource management, and earned value management.

 

NEW QUESTION # 26
Determine the correct formula and date for the late finish for Activity 2002.

  • A. LS.2003 - 1 day -> 10-06-01.
  • B. LS.2003 + 1 day -> 10-07-01.
  • C. LS.2003 - 1 day -> 11.06.01.
  • D. LS.2003 - 1 day -> 10-05-01.

Answer: D


NEW QUESTION # 27
How many work days does it take to move the product from testing to sale?

  • A. 60.
  • B. 100.
  • C. 70.
  • D. 90.

Answer: B


NEW QUESTION # 28
What owner action could have mitigated the late completion of the project?

  • A. Hire a more senior project manager.
  • B. Use a procurement agent to monitor and expedite equipment deliveries.
  • C. Self-perform more of the work.
  • D. Prepare better structural steel drawings.

Answer: B


NEW QUESTION # 29
What is a key first step in developing a critical path method schedule?

  • A. Drawing the logic diagram.
  • B. Drawing a bar chart of the key phrases of the work.
  • C. Setting out the resource to be used and its limitations.
  • D. Defining the execution plan to meet the required scope of work.

Answer: A


NEW QUESTION # 30
If Activity E's duration changes to 4 months, what is the overall duration of the project.

  • A. 20 months.
  • B. 21 months.
  • C. 19 months.
  • D. 22 months.

Answer: A


NEW QUESTION # 31
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?

  • A. 2003,8001.9001.9002,9005,10001
  • B. 5001,7001.8001,9001,9004,9005
  • C. 6001, 8001, 9001. 9002, 9004. 9005
  • D. 7001, 8001, 9001. 9003. 9004. 10002

Answer: C


NEW QUESTION # 32
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

  • A. 09-28-01.
  • B. 09-18-01.
  • C. 09-15-01.
  • D. 09-08-01.

Answer: D


NEW QUESTION # 33
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

  • A. 2 cranes
  • B. 4 cranes
  • C. 3 cranes
  • D. 1 crane

Answer: A


NEW QUESTION # 34
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?

  • A. 09 Sep 2021
  • B. 27 Aug 2021
  • C. 19 Sep 2021
  • D. 08 Sep 2021

Answer: C


NEW QUESTION # 35
What was the original planned duration for Activity A through Activity G?

  • A. 25.
  • B. 28.
  • C. 26.
  • D. 24.

Answer: B


NEW QUESTION # 36
In its simplest form, what is the main drawback of critical path method scheduling?

  • A. It requires a backward pass to calculate late dates.
  • B. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
  • C. It doesn't account for interdependent between activities.
  • D. It assumes that resources are unlimited.

Answer: D


NEW QUESTION # 37
The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.

  • A. uses arrows to signify logic in a network
  • B. allows more than one critical path to be represented
  • C. allows multiple relationship types to be associated with activities
  • D. can be used to calculate the late start and late finish of all activities

Answer: A


NEW QUESTION # 38
If Activity E's duration changes to 4 months, what is the overall duration of the project.

  • A. 20 months.
  • B. 21 months.
  • C. 19 months.
  • D. 22 months.

Answer: A


NEW QUESTION # 39
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

  • A. 407 days
  • B. 362 days
  • C. 267 days
  • D. 255 days

Answer: A


NEW QUESTION # 40
Which of the following statements is true?

  • A. In the absence of contrary contractual language total float, as opposed to tree float, there is a commodity belonging to the owner
  • B. In the absence of contrary contractual language network float, as opposed to project float, there is a shared commodity between the owner and contractor
  • C. In the absence of a contrary contractual language total float, as opposed to free float, there is a commodity belonging to the contractor
  • D. In the absence of contrary contractual language free float, as opposed to project float, there is not a shared commodity between the owner and the contractor

Answer: B


NEW QUESTION # 41
Which of the following will always describe the critical path? The path with

  • A. Zero float.
  • B. Negative float.
  • C. The shortest duration and negative float.
  • D. The longest duration through the network.

Answer: A


NEW QUESTION # 42
Determine the correct formula and date for the late finish for Activity 9004.

  • A. LS.10002 - 1 day -> 11-27-03.
  • B. LS.10002^ Lag.7 + i day -> 11-20-03.
  • C. LS.10002 + 1 day -> 11-29-03.
  • D. LS.10002 - Lag.7 - l day -> 11-20-03.

Answer: B


NEW QUESTION # 43
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

  • A. Acceleration.
  • B. Production output.
  • C. Productivity efficiency.
  • D. Productivity loss.

Answer: D


NEW QUESTION # 44
Why does activity 1001 have two successor activities?

  • A. Because the duration of activities 2001, 2002 and 200.f require two successors
  • B. Because the late finish of 1001 and the late start of 7001 require two successors
  • C. Because there are two defined logic paths for the work
  • D. Because the problem could not effectively work with only one successor

Answer: C


NEW QUESTION # 45
......

Verified AACE-PSP dumps Q&As - 100% Pass from Fast2test: https://www.fast2test.com/AACE-PSP-premium-file.html

Pass AACE-PSP Exam in First Attempt Guaranteed 2025 Dumps: https://drive.google.com/open?id=1SFqgoaECKf66AOgu2dMBX_hR0EBJNqBQ

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어