AACE International AACE-PSP Certification Exam is a rigorous and highly respected certification program that demonstrates a candidate's knowledge and expertise in project planning and scheduling. Planning & Scheduling Professional (PSP) Exam certification is recognized globally and is highly valued by employers in the construction, engineering, and related industries. Passing the exam requires a strong understanding of project management principles and techniques, as well as a commitment to ongoing professional development.
To be eligible for the AACE-PSP certification, candidates must have a minimum of four years of professional experience in planning and scheduling. They must also have a bachelor's degree from an accredited institution, or a combination of education and experience that equals four years. Planning & Scheduling Professional (PSP) Exam certification exam consists of 120 multiple-choice questions, which cover topics such as project planning, scheduling, resource management, and earned value management.
NEW QUESTION # 26
Determine the correct formula and date for the late finish for Activity 2002.
- A. LS.2003 - 1 day -> 10-06-01.
- B. LS.2003 + 1 day -> 10-07-01.
- C. LS.2003 - 1 day -> 11.06.01.
- D. LS.2003 - 1 day -> 10-05-01.
Answer: D
NEW QUESTION # 27
How many work days does it take to move the product from testing to sale?
- A. 60.
- B. 100.
- C. 70.
- D. 90.
Answer: B
NEW QUESTION # 28
What owner action could have mitigated the late completion of the project?
- A. Hire a more senior project manager.
- B. Use a procurement agent to monitor and expedite equipment deliveries.
- C. Self-perform more of the work.
- D. Prepare better structural steel drawings.
Answer: B
NEW QUESTION # 29
What is a key first step in developing a critical path method schedule?
- A. Drawing the logic diagram.
- B. Drawing a bar chart of the key phrases of the work.
- C. Setting out the resource to be used and its limitations.
- D. Defining the execution plan to meet the required scope of work.
Answer: A
NEW QUESTION # 30
If Activity E's duration changes to 4 months, what is the overall duration of the project.
- A. 20 months.
- B. 21 months.
- C. 19 months.
- D. 22 months.
Answer: A
NEW QUESTION # 31
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?
- A. 2003,8001.9001.9002,9005,10001
- B. 5001,7001.8001,9001,9004,9005
- C. 6001, 8001, 9001. 9002, 9004. 9005
- D. 7001, 8001, 9001. 9003. 9004. 10002
Answer: C
NEW QUESTION # 32
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
- A. 09-28-01.
- B. 09-18-01.
- C. 09-15-01.
- D. 09-08-01.
Answer: D
NEW QUESTION # 33
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
- A. 2 cranes
- B. 4 cranes
- C. 3 cranes
- D. 1 crane
Answer: A
NEW QUESTION # 34
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?
- A. 09 Sep 2021
- B. 27 Aug 2021
- C. 19 Sep 2021
- D. 08 Sep 2021
Answer: C
NEW QUESTION # 35
What was the original planned duration for Activity A through Activity G?
- A. 25.
- B. 28.
- C. 26.
- D. 24.
Answer: B
NEW QUESTION # 36
In its simplest form, what is the main drawback of critical path method scheduling?
- A. It requires a backward pass to calculate late dates.
- B. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
- C. It doesn't account for interdependent between activities.
- D. It assumes that resources are unlimited.
Answer: D
NEW QUESTION # 37
The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.
- A. uses arrows to signify logic in a network
- B. allows more than one critical path to be represented
- C. allows multiple relationship types to be associated with activities
- D. can be used to calculate the late start and late finish of all activities
Answer: A
NEW QUESTION # 38
If Activity E's duration changes to 4 months, what is the overall duration of the project.
- A. 20 months.
- B. 21 months.
- C. 19 months.
- D. 22 months.
Answer: A
NEW QUESTION # 39
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
- A. 407 days
- B. 362 days
- C. 267 days
- D. 255 days
Answer: A
NEW QUESTION # 40
Which of the following statements is true?
- A. In the absence of contrary contractual language total float, as opposed to tree float, there is a commodity belonging to the owner
- B. In the absence of contrary contractual language network float, as opposed to project float, there is a shared commodity between the owner and contractor
- C. In the absence of a contrary contractual language total float, as opposed to free float, there is a commodity belonging to the contractor
- D. In the absence of contrary contractual language free float, as opposed to project float, there is not a shared commodity between the owner and the contractor
Answer: B
NEW QUESTION # 41
Which of the following will always describe the critical path? The path with
- A. Zero float.
- B. Negative float.
- C. The shortest duration and negative float.
- D. The longest duration through the network.
Answer: A
NEW QUESTION # 42
Determine the correct formula and date for the late finish for Activity 9004.
- A. LS.10002 - 1 day -> 11-27-03.
- B. LS.10002^ Lag.7 + i day -> 11-20-03.
- C. LS.10002 + 1 day -> 11-29-03.
- D. LS.10002 - Lag.7 - l day -> 11-20-03.
Answer: B
NEW QUESTION # 43
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:
- A. Acceleration.
- B. Production output.
- C. Productivity efficiency.
- D. Productivity loss.
Answer: D
NEW QUESTION # 44
Why does activity 1001 have two successor activities?
- A. Because the duration of activities 2001, 2002 and 200.f require two successors
- B. Because the late finish of 1001 and the late start of 7001 require two successors
- C. Because there are two defined logic paths for the work
- D. Because the problem could not effectively work with only one successor
Answer: C
NEW QUESTION # 45
......