NEW QUESTION 45
What is the free float for Activity F?

  • A. 0months.
  • B. 1months.
  • C. 3 months.
  • D. 2month.

Answer: A

 

NEW QUESTION 46
Determine the correct formula and date for the late finish for Activity 2002.

  • A. LS.2003 - 1 day -> 10-06-01.
  • B. LS.2003 - 1 day -> 11.06.01.
  • C. LS.2003 - 1 day -> 10-05-01.
  • D. LS.2003 + 1 day -> 10-07-01.

Answer: C

 

NEW QUESTION 47
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

  • A. After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
  • B. After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
  • C. After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.

Answer: B

 

NEW QUESTION 48
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

  • A. Estimating remaining durations of activities.
  • B. The correct recording of actual start dates.
  • C. Entering the time impacts of delays and change orders.
  • D. Making "downstream" logic revisions as required.

Answer: D

 

NEW QUESTION 49
At the end of month one, did the delay to the parking structure foundation delay the project?

  • A. Yes, by 14 calendar days.
  • B. Yes, by 4 calendar days.
  • C. NO.
  • D. Yes, by 9 calendar days.

Answer: B

 

NEW QUESTION 50
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

  • A. Certain activities in the critical path have no successors.
  • B. The schedule has too much detail to reflect an accurate critical path.
  • C. Different calendars are assigned to certain activities in the logical chain.
  • D. The schedule is projecting an "early completion".

Answer: A

 

NEW QUESTION 51
Which of the following will always describe the critical path? The path with

  • A. The longest duration through the network.
  • B. Negative float.
  • C. Zero float.
  • D. The shortest duration and negative float.

Answer: C

 

NEW QUESTION 52
Resource planning must take all of the following into account except for

  • A. Time available to complete the project.
  • B. Types of materials, equipment and labor skills required to complete the project.
  • C. Cash flow (expenditure) limitations for completing work on the project.
  • D. Earned value techniques established for the project.

Answer: D

 

NEW QUESTION 53
Determine the correct formula and date for the late start for Activity 9001.

  • A. LF.9001 Dur.9001 -> 11-20-02.
  • B. The early finish is required in order to determine the answer.
  • C. There is insufficient data provided to calculate the answer.
  • D. LS.6001 Dur.6001 -> 11-20-02.

Answer: A

 

NEW QUESTION 54
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

  • A. 91 days
  • B. 168 days
  • C. 183 days
  • D. 193 days

Answer: C

 

NEW QUESTION 55
All the following describe the critical path of a schedule EXCEPT:

  • A. Determined by network logic and is the chain of activities that controls the overall project completion time.
  • B. Frequently defined as the shortest path through the schedule.
  • C. Changed by redefining the network logic or changing activity durations or both.
  • D. The series of activities having the least amount of total float.

Answer: B

 

NEW QUESTION 56
How could the structural steel drawing delay have been prevented?

  • A. Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
  • B. Switch to post-tensioned concrete construction.
  • C. Add a time buffer at the end of structural steel activities.
  • D. Allow adequate time for review and resubmittal in the baseline schedule.

Answer: C

 

NEW QUESTION 57
Identify the minimum project duration.

  • A. 20 months.
  • B. 21 months.
  • C. 16 months.
  • D. 19 months.

Answer: A

 

NEW QUESTION 58
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

  • A. 48 lifts
  • B. 24 lifts
  • C. 36 lifts
  • D. 30 lifts

Answer: C

 

NEW QUESTION 59
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.

  • A. Estimate at completion (EAC)
  • B. Budget at completion (BAC)
  • C. Budgeted cost of work scheduled (BCWS)
  • D. Budgeted cost of work performed (BCWP)

Answer: B

 

NEW QUESTION 60
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

  • A. B.
  • B. C.
  • C. W.
  • D. S.

Answer: D

 

NEW QUESTION 61
Project delays are best analyzed

  • A. Contemporaneously with the delay.
  • B. Late in the project.
  • C. By an expert after the project is finished when complete records are available and the impact is known.
  • D. After either the contractor or the owner acknowledges ^responsibility for the delay.

Answer: C

 

NEW QUESTION 62
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

  • A. 362 days
  • B. 255 days
  • C. 407 days
  • D. 267 days

Answer: C

 

NEW QUESTION 63
Which activity is drawn in the incorrect position?

  • A. Activity D.
  • B. Activity E.
  • C. Activity C.
  • D. Activity G.

Answer: A

 

NEW QUESTION 64
How many work days does it take to move the product from testing to sale?

  • A. 90.
  • B. 60.
  • C. 70.
  • D. 100.

Answer: D

 

NEW QUESTION 65
......

AACE-PSP EXAM DUMPS WITH GUARANTEED SUCCESS: https://www.fast2test.com/AACE-PSP-premium-file.html

Best Quality AACE International AACE-PSP Exam Questions: https://drive.google.com/open?id=1_8ha1mcZtVOeiY7GUxT2Vo48UzC27qek

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 ) From Monday to Saturday

Support: Contact now 

日本語 Deutsch 繁体中文 한국어