NEW QUESTION 40
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.
- A. Basic dates for activities
- B. Internally processed activities
- C. Document information records
- D. Relationships
- E. Material components
Answer: B,D,E
NEW QUESTION 41
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
- A. The control key
- B. The scheduling parameters for the network
- C. The table of MRP controllers
- D. The network profile
Answer: B
NEW QUESTION 42
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are
3 correct Answers to this question.
- A. Stock transfer posting
- B. Generate purchase requisition
- C. Cancel goods issue
- D. Confirm production order
- E. Generate delivery
Answer: A,B,E
NEW QUESTION 43
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Network profile
- B. Network type
- C. Project profile
- D. Data entry profile
Answer: D
NEW QUESTION 44
Which object is used to allocate the costs from a claim to the project structure?
- A. Internal order
- B. Network activity
- C. Claim
- D. WBS element
Answer: A
NEW QUESTION 45
Which planning method can prevent further rescheduling of activities?
- A. Workforce planning
- B. Partial confirmation of activities
- C. Capacity requirements activation
- D. Capacity leveling
Answer: C
NEW QUESTION 46
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.
- A. Resource
- B. Production version
- C. Location
- D. Material
Answer: A,C
NEW QUESTION 47
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?
- A. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
-> Purchase order monitoring -> Goods receipt -> Invoice receipt - B. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
- C. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
- D. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
Answer: D
NEW QUESTION 48
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
- A. Forecast dates of the WBS
- B. Basic dates of the WBS
- C. Basic dates of the network activity
- D. Actual dates of the network activity
Answer: C
NEW QUESTION 49
Where do you maintain the length of the project ID?
- A. Project type
- B. Project profile
- C. Special characters
- D. Project coding mask
Answer: D
NEW QUESTION 50
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.
- A. Background activation (CJBV - Activate Availability Control)
- B. Automatic activation with budget assignment
- C. Automatic activation with the first actual posting
- D. Automatic activation with assignment to an investment program
Answer: A,B
NEW QUESTION 51
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
- A. Activity
- B. Milestone
- C. Activity element
- D. Network header
Answer: A
NEW QUESTION 52
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
- A. Material master
- B. WBS element
- C. Network activity
- D. BOM item
Answer: C,D
NEW QUESTION 53
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.
- A. Baseline dates
- B. Forecast dates
- C. Planned dates
- D. Basic dates
Answer: B,D
NEW QUESTION 54
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing budget for material components
- B. Missing material availability
- C. Missing reservations for material components
- D. Missing authorizations to release material components
Answer: D